Baltimore, MD

Zurich Insurance Group, New Parking Garage

Scope/Solutions

Zurich’s facility improvement plan required additional parking for over 1,000 vehicles and needed the parking structure to be operational within sixteen months from the start of design. SGH served as the prime design professional for this 1,100 car, four-story concrete parking structure.

The plan required that the structure be built partially below grade. SGH designed the 340,000 sq ft structure that consists of a cast-in-place, post-tensioned concrete superstructure with deep-belled caisson foundations, a permanent tied-back wall to retain earth at below-grade portions of the structure, and three vehicle link bridges between the garage and the adjacent roadways. Our services included the following:

  • Performed a fast-track design of the superstructure, foundations, link bridges, and tied-back retaining wall with capacity for future expansion
  • Managed the team of design professionals for architecture and other engineering disciplines
  • Worked closely with the owner and the construction manager throughout the design and construction process to keep the project on schedule and under budget
  • Prepared a life-cycle cost analysis of various durability measures and assisted the client with selection of the most suitable protection measures

SGH concrete technologists and laboratory personnel worked closely with the concrete supplier and concrete contractor to refine mix designs and placement and finishing procedures to assure an aesthetically pleasing and durable concrete structure.

Project Summary

Icon: completion-date

1999

Completion Date
Solutions
New Construction
Services
Structures | Applied Science & Research
Markets
Infrastructure & Transportation
Client(s)
Zurich North America
Specialized Capabilities
Building Design | Materials Science

Additional Projects

Mid-Atlantic

Ronald Reagan National Airport

Parson's Management, the owner's project manager, retained SGH to consult on the design of the building enclosure for the new terminal building, including curtain walls, skylights, windows, and metal and thermoplastic roof systems.
Explore
Mid-Atlantic

The Colonade Apartments Parking Structure Demolition

A portion of The Colonade’s parking structure, constructed with precast concrete plank supported on precast prestressed concrete beams, was beyond repair.  SGH worked with the demolition contractor to develop construction documents for the selective demolition of the structure. 
Explore