Cedarmere was named by William Cullen Bryant, who purchased the forty-acre property in 1843. Bryant constructed the mill in 1862 in the Gothic Revival style. Page Ayres Cowley Architecture was leading a major restoration to the mill and observed sagging roof rafters around an infilled skylight and a deteriorated valley rafter. SGH evaluated the existing roof framing conditions and helped develop structural strengthening.
Highlights of our work include the following:
- Reviewing available documents to understand the planned work and the existing conditions
- Visiting the site to document the roof framing
- Analyzing the roof structure, including the effects of the chimney leaning on the roof framing
- Developing details to strengthen the sagging rafters around the skylight, supplement the deteriorated valley rafter, and reinforce the existing roof truss connections
- Designing repairs for existing masonry walls
- Collaborating with the architecture team to develop details that would provide the necessary structural capacity, while retaining as much of the historic fabric as possible
Project Summary
Solutions
Repair & Rehabilitation | Preservation
Services
Structures | Building Enclosures
Markets
Culture & Entertainment
Client(s)
Page Ayres Cowley Architecture
Specialized Capabilities
Repair & Strengthening | Preservation
Key team members
Additional Projects
Northeast
New Museum of Contemporary Art
The New Museum of Contemporary Art is the first major art museum constructed from the ground up in Lower Manhattan. SGH was the structural engineer of record and consulted on the building enclosure design for the 60,000 sq ft, eight-story building.
Northeast
American Museum of Natural History, Richard Gilder Center for Science, Education, and Innovation
The Gilder Center expands access to a broader range of AMNH's resources for students, teachers, and families, offering new learning opportunities and inviting visitors to share in the excitement of discovery. SGH consulted on fire life safety code requirements for the project.