PLAYA VISTA, CA
Building 3 at Water’s Edge
Scope/Solutions
Water’s Edge is a three-building creative-office campus. The six-story Building 3, also known as WE3, features a custom aluminum screen that filters sunlight to make it more functional as interior lighting. Tenants enjoy flexible office space, balconies, an upper level garden, outdoor meeting areas, and below-grade parking. SGH consulted on the building enclosure and fire life safety design.
SGH consulted on the design of below-grade, podium, walkway, and balcony waterproofing; curtain walls; exterior walls; and roofing. Highlights of our work include:
- Reviewing the proposed design, helping select systems, and suggesting ways to improve performance
- Developing performance criteria and recommending a mockup and testing scope
- Preparing details to integrate the various assemblies and transition between horizontal and vertical surfaces
- Evaluating alternate below-grade waterproofing options and helping the team develop details to address below-grade conditions
- Providing construction phase services, including reviewing contractor submittals, visiting the site to observe ongoing construction, and helping address field conditions
We also assisted with the fire life safety design, including:
- Reviewing the design’s compliance with applicable code and fire life safety requirements
- Evaluating egress and exit access, occupant load, and fire resistance rating approaches and developing fire life safety plans
- Helping the project team develop alternate means-and-methods approaches for exiting the Level 4 Sky Garden, outdoor soccer field occupancy loading, and protecting the elevator/lobby hoistway opening
- Analyzing exterior egress balconies, stair capacity, open-air ventilation, smoke movement, automatic sprinkler protection, and operational occupant load controls
Project Summary
Solutions
New Construction
Services
Performance & Code Consulting | Building Enclosures
Markets
Commercial
Client(s)
Studio Pali Fekete: Architects
Specialized Capabilities
Roofing & Waterproofing | Fire Life Safety & Accessibility
Key team members
Additional Projects
West
Central Marin Sanitation Agency, Administration Building
The building's metal panel roofing had exceeded its useful life and needed to be replaced. The agency retained SGH to design the roof replacement.
West
1101 Second Avenue
As a precondition for restoring the building to occupancy, the City of Seattle required a seismic upgrade of the building to Life Safety performance under design earthquake shaking.