New York, NY

141 East Houston Street

Scope/Solutions

Constructed on the site of the Sunshine Cinema on the Lower East Side, the new glass-clad building offers boutique office space and ground-level retail. The 65,000 sq ft building steps back to blend with the surrounding streetscape and create a landscaped terrace. SGH consulted on the demolition of the existing theater, served as the structural engineer of record for the new building, and consulted on the building enclosure design.

The $52 million project included demolishing the existing theater, which had been reconstructed in 2001. SGH helped the demolition and temporary-shoring engineer locate bracing to least affect the new foundation, designed permanent supports for the party wall supporting an adjacent brownstone, and designed the new nine-story structure with two subgrade levels. Highlights of our structural design include:

  • Mat foundation with a concrete liner wall inboard of the theater’s foundation wall
  • Concrete beam at the top of the foundation wall extending over the existing foundation wall to the property line
  • Sloped steel columns extending from pilasters inboard of the liner wall to the property line at the second floor
  • Lateral system designed for the gravity eccentricity from the sloped columns in addition to wind and seismic forces
  • Structural steel superstructure with braced frames and concrete slabs on metal deck
  • Unbraced 60 ft tall columns supporting an ivy-and-vegetative wall in Sunshine Alley
  • Support for the articulated glass enclosure

We also consulted on the design of the building enclosure, including below-grade and terrace waterproofing, floor-to-ceiling curtain walls, aluminum-composite wall panels, and roofing. Highlights of our work include:

  • Reviewing the proposed design and helping select systems, considering strength, durability, and cost
  • Developing details to integrate adjacent enclosure systems, including a large exterior entry structure, and to address unique floor line conditions
  • Performing a building enclosure trade-off analysis to demonstrate energy code compliance
  • Analyzing heat and moisture migration for the typical building enclosure components to identify the optimal locations of air and vapor barriers to mitigate condensation
  • Calculating thermal/solar performance data used by the mechanical engineer to determine equipment sizes

SGH provided structural and building enclosure construction-phase services.

Project Summary

Icon: completion-date

2022

Completion Date
Solutions
New Construction
Services
Structures | Building Enclosures | Performance & Code Consulting
Markets
Commercial | Mixed-Use
Client(s)
East End Capital
Specialized Capabilities
Building Design | Facades & Glazing | Roofing & Waterproofing | Energy & Sustainability

Key team members

Smiling gray-haired man wearing glasses, a dark suit, blue shirt, and patterned tie
Kevin Poulin
Principal
Sean O'Brien
Managing Principal, Building Technology, New York

Additional Projects

Northeast

303 Congress Street

The six-story, steel-moment framed building at 303 Congress Street was constructed in 1983. In 1995, SGH investigated foundation settlement that caused significant damage and resulted in immediate evacuation of the building.
Explore
Northeast

New Hampshire State House

The monumental dome on the New Hampshire State House is gilded in gold leaf. After regilding in the early 1990s, the gold leaf started discoloring. SGH investigated the discoloration and subsequently worked on the regilding project.
Explore