Boston, MA
Flood Assessment
Scope/Solutions
In response to an assessment by the Boston Water and Sewer Commission projecting local and urban flooding in parts of campus might become more frequent and severe in the future, SGH was retained to review flood hazard data and assess the vulnerability of campus buildings and structures.
SGH assessed all campus buildings and associated equipment, utility tunnels, roofs, and pertinent below-grade areas. Highlights of our work include:
- Visually surveying the structures to identify the most vulnerable
- Analyzing the existing campus topography to locate areas with ponding potential
- Establishing a vulnerability rating for each structure based on a combination of the likelihood of occurrence of flooding and the consequence
- Developing concepts for reducing risk from drainage issues or local flooding at several locations we determined to be vulnerable
Project Summary
Solutions
Repair & Rehabilitation
Services
Structures | Performance & Code Consulting
Markets
Education
Client(s)
Confidential University
Specialized Capabilities
Geotechnical | Risk & Resilience
Additional Projects
Northeast
Worcester Polytechnic Institute, Sports and Recreation Center
Recognizing sports and fitness are important to the campus community, Worcester Polytechnic Institute (WPI) wanted to update its current facilities by constructing a new sports and recreation center. SGH was the precast specialty engineer for the natatorium.
Northeast
Fitchburg State University, Science Facility Modernization
Originally constructed in 1963, the three-story Condike Science Building needed renovations to improve the performance and function of the facility. SGH was the Building Enclosure Commissioning Agent (BECxA) for the project.