Massachusetts Water Resource Authority, Walnut Hill Treatment Plant, Cosgrove Intake Pipeline

Marlborough, MA

Client

Barletta Heavy Division, Inc.

Completion

2004

The Cosgrove Intake pipeline, a 144 in. dia. prestressed concrete cylinder pipe (PCCP), at MWRA’s Walnut Hill Water Treatment Plant Project was completed in early 2004 as a part of the water supply system for the City of Boston. Less than a year after construction of the pipeline, a large leak of approximately 700 gpm developed near a deep manhole chamber in a section of the pipeline with multiple elbows. SGH provided emergency response and evaluated the risk of failure resulting from the leak, inspected the pipeline to determine the cause of the leak, and developed a repair scheme.