With its Kendall Square development, MIT creates a community shared by institute resources and private companies. The Site 3 project incorporates an existing Kendall Building at 238 Main Street with a new twelve-story addition, offering modern office and laboratory space and ground-level retail. A five-story atrium connects the new and existing structures. SGH provided building enclosure commissioning services for the building featuring high-performance unitized curtain wall systems and existing mass masonry walls.
As the building enclosure commissioning provider, SGH worked with the project team from the design documents phase through mockups, performance testing, and construction. Highlights of our work include the following:
- Helping establish performance expectations by developing the building enclosure commissioning (BECx) plan and specification and outlining testing requirements, roles and responsibilities for the project team, and procedures for documenting and resolving construction-related issues
- Reviewing the enclosure design, including the owner’s project requirements and the basis of design at critical phases, and providing recommendations to improve performance, energy efficiency, and constructability
- Reviewing enclosure-related submittals, including those outlining plans for the curtain wall performance mockup construction and testing, and operation and maintenance manuals
- Visiting the unitized curtain wall fabricator’s facility to observe the construction processes and review their QA/QC plan
- Providing construction phase services, including coordinating commissioning activities, observing ongoing construction and in situ performance testing to compare with the design intent, and helping resolve field conditions
- Preparing a final BECx report summarizing completed work, construction deviations, and site observations
- Performing a follow-up review of the enclosure ten months after occupancy
Project Summary
Solutions
New Construction
Services
Building Enclosures
Markets
Commercial | Education | Health Care & Life Sciences
Client(s)
MITIMCo (MIT)
Specialized Capabilities
Commissioning
Key team members

Additional Projects
Northeast
Stop & Shop
Shop & Stop Store #539 is constructed with a rooftop parking deck over the supermarket. SGH was the engineer of record for a new split-slab waterproofing system design, and also evaluated and developed repairs to address concealed damage to the building structure and parking deck.
Northeast
303 Congress Street
The six-story, steel-moment framed building at 303 Congress Street was constructed in 1983. In 1995, SGH investigated foundation settlement that caused significant damage and resulted in immediate evacuation of the building.