Northeast
Saint Francis Hospital and Medical Center
SGH assessed the condition of Building 3, investigated the cause of movement, and developed remediation options allowing construction to proceed.
Winchester, MA
Scope/Solutions
The parking garage at Winchester Hospital was constructed in 1982 and is used heavily during the day by patients and visitors. The concrete structure, primarily comprising precast double-tees, beams, and columns, exhibited cracking and spalling. SGH investigated the structure’s condition and designed repairs to extend its useful life.
SGH determined the structure required remedial work to address corrosion‑related deterioration and designed repairs, including:
We helped Winchester Hospital coordinate scheduling and implement the project in phases, allowing the garage to remain open during the work.
Project Summary