Boston, MA
Logan International Airport, I-90/Route 1A Interchange
Scope/Solutions
The modernization of Logan International Airport included the new I-90/Route 1A Interchange. SGH assisted several contractors that looked for assistance with understanding the complex system of reinforcement, post-tensioning ducts and anchorages, and conduits, as well as with concrete quality at a drilled shaft.
The elevated roadways are constructed of cast-in-place, post-tensioned concrete box girders and supported on individual concrete columns, concrete bents, and concrete abutments. The columns are supported on large diameter drilled shafts. SGH provided construction engineering services, including the following:
- Preparation of reinforcing bar shop drawings for box girders and straddle bents for direct use in fabrication, reducing delivery time by several weeks
- Preparation of integrated drawings of box girders and straddle bents showing post-tensioning ducts, anchorages and reinforcement, block outs, reinforcing steel, anchor bolts, earthquake restrainers, drainage systems, and utility conduits to help resolve conflicts between embedded items in advance of construction
- Evaluation of concrete quality in a major drilled shaft using extracted deep core samples
- Evaluation of out-of-tolerance drilled shaft reinforcement to show that the drilled shaft was able to carry design loads safely
- Evaluation and repair design for missing post-tensioning bars in one of the straddle bents
Project Summary
Solutions
New Construction
Services
Structures
Markets
Infrastructure & Transportation
Client(s)
Barletta Heavy Division
Specialized Capabilities
Temporary Construction
Key team members


Additional Projects
Northeast
MWRA, Spot Pond
SGH developed an emergency repair for a 48 in. dia. prestressed concrete cylinder pipeline penetrating the concrete core of the Spot Pond Dam. The pipe was cracked at the penetration point due to ground movement at a nearby bend in the pipeline.
Northeast
Massachusetts Bay Transportation Authority, Charles/MGH Station
As part of the complete rebuilding and reconfiguring of the station, the contractor needed to remove an existing pier supporting the viaduct. SGH designed a load-transfer system that could be installed and utilized within the single weekend shutdown permitted by the MBTA.