West
SR 520 Floating Bridge
Working with the design-build team, SGH served as the structural and marine engineer, as well as the engineer of record for many critical tasks on this project.
Richmond, CA
Scope/Solutions
Originally built in the 1950s, the timber terminal was becoming increasingly costly to maintain and was no longer considered fit-for-purpose for seismic and berthing requirements. Instead of embarking on an incremental improvement program, the terminal owner sought to build a new steel wharf over the existing, while maintaining operability through construction. SGH prepared conceptual designs and developed design criteria for replacement of the entire marine terminal.
SGH acted as the owner’s engineer throughout the design/build project and represented the owner for permitting reviews. We worked closely with terminal staff and marine contractors to complete the following:
Project Summary