The 1210-30 Washington Street Garage is a three-level reinforced concrete parking structure with approximately 25,000 sq ft per level. The two-way slabs are supported by interior concrete columns with capitals and exterior concrete masonry...
The Jamaicaway Towers Parking Garage required extensive concrete demolition and repair due to widespread deterioration of the structural elements. P.J. Spillane engaged SGH to develop and design means and methods to provide temporary support...
Fountain View on the Plaza in Kansas City includes two parking garages, Garage A and Garage B constructed in 1999. Garage A accommodates 406 cars and Garage B accommodates 248 cars. The garages are free-standing, four-story, open parking...
A portion of The Colonade’s parking structure, constructed with precast concrete plank supported on precast prestressed concrete beams, was beyond repair. SGH worked with the demolition contractor to develop construction documents for...
Hartford Hospital needed more employee parking and sought to build a new parking garage. The precast concrete Hudson Street Employee Parking Garage provides 1,250 parking spaces in nine stories. Seeking to achieve economy and an...
The P-405 project consists of a multi-story Bachelor Enlisted Quarters and multi-story parking structure at Naval Base San Diego. The parking structure provides 800 parking spaces in six stories, including one at-grade level and five elevated...
The two-level Reservoir Place parking garage offers 700 parking spaces below three levels of occupied office space and is critical to daily facility operations. The below-grade garage, constructed in the mid-1980s, is a Filigree structure...
A portion of the West Parking Garage fifth floor was cast on a snowy day. When the forms were stripped, contractor observed cracks and ice-filled voids in the slab. The owner and contractor needed to know if the 20,000 sq ft deck could be...
Zurich’s facility improvement plan required additional parking for over 1,000 vehicles and needed the parking structure to be operational within sixteen months from the start of design. SGH served as the prime design professional for this 1...
The Museum of Science parking garage was built in two phases in the late 1960s and partially spans the Charles River. After thirty years of exposure to weather and vehicles, chlorides from deicing salts permeated the top surface of the concrete...