Logan International Airport, West Parking, Controlled Demolition of Post-tensioned Concrete Garage and Slab

Boston, MA

Market: Parking

Client

Modern Continental Construction

Completion

1998

A portion of the West Parking Garage fifth floor was cast on a snowy day. When the forms were stripped, contractor observed cracks and ice-filled voids in the slab. The owner and contractor needed to know if the 20,000 sq ft deck could be repaired or should be replaced.